Workforce Requirements
Efficiency is always an important part of getting the job done, however with certain systems such as Accelera™, the curing time can be much faster than a small crew can handle.
In these instances, it is best not to multi-task and instead bring a properly sized crew for each position.
For best results on a maximum 40-foot wet edge include:
- 1 person mixing
- 1 person running pails
- 1 person on squeegee
- 1 person cross-rolling
- 1 person broadcasting for every 15 linear feet of wet edge
Additional crew members will be required for complex installations requiring cut-in work or when using faster setting resins.