How to Apply Water and Wastewater Coatings in Confined Spaces

Applying protective coatings inside a manhole, tank, wet well or lift station is not the same as coating an open structure. 

The space is tight. Ventilation is limited. The substrate may be damp, chemically damaged or covered with biological growth. Access is often through a single entry point, and the crew working inside is doing so under confined-space entry requirements. At the same time, the coating itself still needs to be mixed correctly, applied at the right film thickness, inspected thoroughly and allowed to cure before the asset returns to service. 

That combination of physical constraints, safety requirements and performance demands makes confined space coating work one of the most technically challenging categories in water and wastewater infrastructure. 

did you know logo

Getting it right matters. Manholes, tanks, wet wells, lift stations and related structures are exposed to hydrogen sulfide gas, sulfuric acid formation, microbial corrosion, constant moisture, abrasion and chemical attack. When a coating fails in one of these environments, the consequences can include accelerated substrate deterioration, leaks, service interruptions and costly emergency repairs. The asset may not be easy to access for inspection, which means failures can go undetected until the damage is significant. 

This article covers what makes confined space coating applications different from other water and wastewater projects, how to plan and execute the work safely and effectively, which coating technologies are commonly used in these environments and what to look for during inspection. 

In this article: 

  • Why Confined Spaces Create Unique Coating Challenges 
  • Confined Space Safety Requirements for Coating Projects 
  • Coating Technologies Used in Confined Water and Wastewater Structures 
  • Step-by-Step Application Process 
  • Inspection and Documentation 
  • FAQs 

Why Confined Spaces Create Unique Coating Challenges

Limited Access and Working Room

Manholes are typically 24 to 36 inches in diameter. Tanks may have a single access hatch. Wet wells and lift stations can require applicators to work in cramped conditions with limited ability to maneuver equipment, position spray guns correctly or maintain consistent technique across the full surface. 

Atmospheric Hazards

Hydrogen sulfide gas is a particular concern in wastewater structures. It is heavier than air, accumulates in low points and can reach dangerous concentrations without warning. Even at low concentrations, it impairs the sense of smell. Carbon dioxide and methane can also be present. Any confined space in a wastewater system must be treated as a potentially hazardous atmosphere until continuous air monitoring confirms otherwise. 

Moisture and Substrate Conditions

Concrete inside manholes, wet wells and tanks is often damp or wet. Groundwater infiltration can make it difficult to achieve the dry substrate conditions many coating systems require. Biological growth, scale, grease and residual wastewater chemistry must be fully removed before any coating is applied. 

Ventilation Limitations

Many coatings generate vapors during application and cure that must be diluted and exhausted from the space. Inadequate ventilation raises the risk of vapor accumulation to hazardous levels and can disrupt the cure process, particularly for systems sensitive to humidity or temperature. 

Confined Space Safety Requirements for Coating Projects

Safety is not a preliminary step in confined space coating work. It is the framework within which every other decision is made. Before any surface preparation or coating application begins, the project team must have a complete confined space safety plan in place and verified. 

OSHA's confined space entry standard (29 CFR 1910.146) governs permit-required confined space entry for general industry. Many water and wastewater structures qualify as permit-required confined spaces because they contain or have the potential to contain a hazardous atmosphere. Compliance with this standard is not optional, and the requirements are detailed. 

Key Safety Requirements Before Entry

Atmospheric Testing: Oxygen content, flammable gases and toxic gases must be tested before entry and monitored continuously throughout the work. 

Ventilation: Mechanical ventilation must be established and maintained. Ventilation rates must account for both worker safety and the vapors generated by the coating system. 

Permit System: A written confined space entry permit must be completed, reviewed and posted before entry. 

Attendant: A trained attendant must remain outside the space at all times, monitoring conditions and maintaining communication. 

PPE: Depending on the atmosphere and coating system, PPE may include supplied-air respirators, chemical-resistant gloves, protective clothing, eye protection and fall protection. 

Coating-Specific Safety Considerations

The coating system selected for a confined space application affects the safety planning. Solvent-based coatings generate higher VOC concentrations than 100% solids systems, which can increase ventilation requirements and the risk of flammable vapor accumulation. Many water and wastewater coating projects in confined spaces specify 100% solids or low-VOC systems specifically because they reduce solvent-related concerns in enclosed environments. 

That said, even low-VOC or 100% solids coatings still require proper ventilation, air monitoring and PPE. Low VOC is not the same as no risk. Product data sheets and safety data sheets must be reviewed before any coating material is brought into a confined space, and the safety plan must account for the specific hazards associated with the chosen system. 

Coating Technologies Used in Confined Water and Wastewater Structures

Not every coating system is well suited for confined space application. Product selection must account for the exposure conditions inside the structure, the substrate type and condition, the available maintenance window and the specific constraints of working in a confined space. 

High-Build 100% Solids Epoxy Linings

High-build, 100% solids epoxy systems are among the most widely used coatings for confined water and wastewater structures. They offer strong adhesion to concrete and steel, excellent chemical resistance, low permeability and the ability to achieve significant dry film thickness in fewer coats. Because they contain little to no solvent, they generate lower VOC concentrations during application and cure, which is a meaningful advantage in enclosed spaces where ventilation is limited. 

These systems are commonly used in manholes, wet wells, lift stations, influent channels, concrete tanks and other structures exposed to hydrogen sulfide gas, sulfuric acid formation, microbial corrosion and wastewater immersion. 

High-Build 100% Solids Polyurethane Linings

High-build, 100% solids polyurethane systems offer crack-bridging flexibility alongside strong chemical resistance and abrasion durability. They are well suited for confined spaces where the concrete substrate has experienced movement, thermal cycling or cracking, and where a rigid epoxy system may not provide adequate flexibility. 

Polyurethane linings are also valued for their fast cure characteristics, which can help reduce the time an asset must remain offline. In confined space projects where the maintenance window is short, a fast-curing polyurethane system may help meet the return-to-service requirement without sacrificing film build or protection. 

Coating System Comparison for Confined Spaces

Why Low-VOC Systems Matter in Confined Spaces

The relationship between coating chemistry and confined space safety is direct. Higher-solvent coatings generate more vapors during application and cure. In a space with limited ventilation, those vapors can accumulate to concentrations that create health hazards, flammability risks or both. 

100% solids and low-VOC coating systems reduce that risk by limiting the amount of volatile material released during application. They do not eliminate the need for ventilation or air monitoring, but they reduce the ventilation demand and the margin for error when conditions inside the space are difficult to control. 

For this reason, many project specifications for confined water and wastewater structures specifically require 100% solids or low-VOC coating systems. 

Step-by-Step Application Process for Confined Space Coatings

A successful confined space coating project does not happen by showing up with a coating and a spray gun. It requires a sequenced process that integrates safety, preparation, application and inspection into a single coordinated effort. Skipping or shortcutting any step creates risk, both for the crew and for the long-term performance of the coating. 

1. Pre-Entry Planning and Hazard Assessment

Before any work begins, the project team should review the confined space entry permit requirements, identify all atmospheric hazards associated with the specific structure, confirm the ventilation plan, verify that rescue equipment and personnel are in place and review the product data sheet and safety data sheet for the coating system being applied. 

This is also the stage to confirm that all equipment is functioning correctly, that mixing ratios and pot life requirements are understood and that the crew has the training and experience needed for the specific application method. 

2. Establish Ventilation and Atmospheric Monitoring

Mechanical ventilation must be established before entry. For coating work in manholes and small tanks, a forced-air blower positioned at the entry point is the most common approach. The blower should supply fresh air into the space—not simply exhaust from it—to ensure that the breathing zone inside is continuously supplied with clean air. 

Continuous atmospheric monitoring must be in place before and throughout the entry. Gas monitors should be calibrated and set to alarm at appropriate thresholds for oxygen, hydrogen sulfide, carbon monoxide and lower explosive limits. Monitoring results should be documented throughout the project. 

3. Surface Preparation

With ventilation established and the space confirmed safe for entry, surface preparation can begin. The sequence is typically: 

  • High-pressure water jetting or cleaning to remove biological growth, scale and contamination 
  • Structural repairs to address deteriorated concrete, active cracks or corroded steel 
  • Mechanical preparation to achieve the required surface profile 
  • Final surface inspection to confirm cleanliness, profile and moisture conditions meet the product requirements 

Do not begin coating application until surface preparation has been inspected and accepted. Any deficiencies identified at this stage are far less costly to address than failures discovered after the coating has been applied and cured. 

4. Material Staging and Mixing

High-build epoxy and polyurethane systems used in confined space applications are typically two-component systems that require precise mixing at the specified ratio. For plural-component spray systems, the equipment must be set up, calibrated and verified outside the space before application begins. 

Pot life is a critical variable in confined space work. Once mixed, the material must be applied within the pot life window. In warm conditions, pot life shortens. In a confined space where the applicator has limited working room, the time required to apply each pass may be longer than on an open structure. The crew must understand the pot life of the specific product and plan accordingly. 

5. Coating Application

Application method inside a confined space depends on the size and geometry of the structure, the coating system selected and the access available. Common methods include: 

  • Brush and roller for small areas, touch-up, stripe coating of welds and edges, and structures where spray application is not practical 
  • Conventional or airless spray for larger tank interiors and structures with adequate access 
  • Plural-component spray for systems that require heated or plural-component equipment 

Regardless of method, wet film thickness should be monitored throughout application using a wet film gauge. Consistent film build across the entire surface is essential. Areas that are difficult to reach—such as the crown of a manhole, the underside of baffles or corners and joints—require extra attention to ensure adequate coverage. 

Stripe coats should be applied to welds, edges, penetrations, joints and other irregular surfaces before the full coat is applied. These areas are prone to thin film build and are common locations for early coating failure. 

6. Cure and Return to Service

After application, the coating must be allowed to cure to the specified level before the asset is returned to service. Cure time depends on the product, the film thickness, the ambient and substrate temperature and the humidity inside the space. 

Ventilation should be maintained throughout the cure period. Some coating systems generate heat or vapors during cure, and adequate airflow helps manage both. Do not return the asset to service before the minimum cure time specified on the product data sheet has been met and confirmed through inspection. 

Inspection and Documentation in Confined Space Coating Projects

Inspection is not a final step performed after the coating has been applied. It is an ongoing process that runs parallel to every phase of the project, from surface preparation through cure verification. 

In confined space coating work, inspection is particularly important because deficiencies are harder to identify after the fact. Once an asset has been returned to service, gaining access for a follow-up inspection requires repeating the full confined space entry process. 

Before Application:

  • Surface cleanliness and profile after preparation 
  • Substrate moisture conditions 
  • Ambient temperature and relative humidity inside the space 
  • Substrate temperature 
  • Confirmation that structural repairs are complete and cured 

During Application:

  • Wet film thickness at regular intervals across the coated surface 
  • Mixing ratios and batch numbers for each component 
  • Pot life monitoring 
  • Consistent coverage of difficult areas including crown, joints, penetrations and corners 
  • Equipment performance and any interruptions to application 

After Application and Cure:

  • Dry film thickness measurements across the full surface 
  • Holiday detection using appropriate voltage for the specified film thickness and product type 
  • Adhesion testing where specified 
  • Visual inspection for pinholes, holidays, runs, sags, missed areas or contamination 
  • Documentation of cure conditions and elapsed cure time before return to service 

Why Documentation Matters

Thorough documentation serves multiple purposes. It provides a record of the work performed that can support warranty claims, inform future maintenance decisions and demonstrate compliance with the project specification. In the event of a coating performance issue, documentation of surface preparation, application conditions, film thickness and cure time is essential for determining what went wrong and why. 

Projects that are documented well tend to perform better. When applicators know that conditions are being recorded, the quality of the work tends to be more consistent. Documentation also creates accountability at every stage of the process. 

At Sherwin-Williams, our technical service team can support confined space coating projects from specification through application and inspection, helping owners, engineers and contractors identify the right system, plan the work correctly and verify that the coating has been applied to the required standard. 

FAQs About Applying Coatings in Confined Water and Wastewater Spaces

What Makes a Space a Confined Space for Coating Purposes?

Under OSHA's confined space standard, a space qualifies if it is large enough to enter, has limited means of entry or exit and is not designed for continuous occupancy. Most manholes, wet wells, tanks and lift stations meet this definition, and most wastewater structures qualify as permit-required because of atmospheric hazards. 

What Coating Systems Work Best Inside Manholes?

High-build 100% solids epoxy linings are the most commonly specified system for manhole rehabilitation due to their strong adhesion to concrete, excellent resistance to hydrogen sulfide and sulfuric acid, low permeability and a low VOC profile. Where the concrete has cracked or moved, 100% solids polyurethane adds crack-bridging flexibility. 

Can Coatings Be Applied to Wet or Damp Concrete Inside a Tank or Manhole?

Some systems are formulated for damp concrete, which is often a practical necessity in these environments. Always confirm acceptable moisture conditions on the product data sheet, and address any active infiltration before coating regardless of the product selected. 

How Long Does It Take to Apply and Cure a Coating Inside a Manhole or Tank?

It depends on structure size, surface preparation scope, the coating system and cure conditions. Surface prep typically takes longer than application. Fast-curing 100% solids systems can reduce total offline time. The product data sheet will specify minimum cure times before return to service. 

Do Confined Space Coating Projects Require Specialized Contractors?

Yes. Applicators need training in both confined space entry and industrial coating application. The skill level of the crew has a direct impact on performance; a high-quality system applied incorrectly will not deliver the service life it is capable of. 

What Are the Most Common Causes of Coating Failure in Confined Water and Wastewater Spaces?

Inadequate surface preparation, application over a damp or contaminated substrate, insufficient film build in hard-to-reach areas and premature return to service are the leading causes of coating failure. Poor ventilation during application and cure can also affect performance. 

How Often Should Coatings in Manholes and Tanks Be Inspected?

Inspection frequency depends on asset type, service conditions, coating system and the owner's asset management program. Early intervention on localized failures is almost always less expensive than a full rehabilitation project. 

Apply Confined Space Water and Wastewater Coatings Right the First Time with Sherwin-Williams

Confined space coating work in water and wastewater infrastructure leaves very little room for error. The access is difficult, the conditions are demanding and the consequences of a coating failure are costly and disruptive to fix. 

The right coating system—applied correctly by a qualified crew under a complete safety plan—can protect manholes, tanks, wet wells, lift stations and other critical structures for a decade or more. That level of performance does not happen by accident. It comes from treating every phase of the project with the same level of care. 

At Sherwin-Williams, we offer coating and lining systems specifically formulated for the confined space environments found throughout water and wastewater infrastructure. Our technical service team can help owners, engineers and contractors select the right system, develop a specification that accounts for the specific conditions of the asset and support the project through application and inspection. 